Sapphire Ice & Leisure

Client: Havering Council

Location: Romford

Contractor: Willmott Dixon

Project Value: £4,800,000

Year Completed: 2017

Suppliers and Products Used:

Gas-fired boilers

CHP unit

underfloor heating,

mechanical ventilation

multiple VRF systems.

Distribution Supply & Extract Ductwork

all power, lighting, data, fire alarms and security.

Kershaw Mechanical Services were contracted to design and install full M&E building services comprising of gas-fired boilers and a CHP unit, underfloor heating, mechanical ventilation and multiple VRF systems. Distribution Supply & Extract Ductwork for the project has been manufactured by Kershaw’s in-house pre-fabrication workshop.  The electrical installation included all power, lighting, data, fire alarms and security.

Pictures: Havering Council