Appointed by Willmott Dixon, Kershaw provided the full MEP works for the new 3 story Central office space for a new headquarters for a leading organisation in the aerospace sector.

The scheme includes a circa £1m hybrid VRF package comprised of 143 fan coil units. This is a far more sustainable and energy-efficient delivery for the VRF as it uses far fewer refrigerant gasses. The building is also ventilated by an expansive ventilation system which is VAV controlled with a CRAC unit installed. Kershaw’s are also responsible for the full Testing and commissioning including the IST Test. The scope for the MEP works includes:

• Ventilation

• VRF A/C

• Drainage

• Internal Rainwater

• Domestic hot/cold water

• Cat 5 Water

• Full BMS control with AM&T monitoring

• Incoming water and gas

• General Lighting

• UPS

• Access Control, Security and CCTV

• LV Switchgear & Incoming electrical Services

• PV Infrastructure

• Fire Alarm